Planned Activities for the Week of 10/4/2021 - 10/10/2021
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Mobilizing pile driving equipment
Site work preparation
Precast concrete piles
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Tower crane erection is tentatively scheduled to take place Wednesday, 10/6 through Saturday, 10/9
Grading and prep at the future MBTA bike shelter & temporary trailer will continue
Eversource’s cable pull off of Somerville Ave to Lot 5 is tentatively scheduled to start
Foundation & waterproofing work will be ongoing adjacent to the building core
Concrete placements will continue at the building core walls & slabs
Support of excavation and stockpile of soils for the deep garage will continue
Subgrade prep for binder paving will continue
MBTA elevator MEP, parapet, glazing and roof work is ongoing
Should you have any questions, please reach out to us at info@discoverUSQ.com.
Thank you,
US2
Gilbane Building Company
Cranshaw Construction