Planned Activities for the Week of 9/20/2021 - 9/26/2021
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Site work for pile installation
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Utility work will continue along Charlestown and at the future MBTA facilities
Eversource’s cable pull off of Somerville Ave to the site is tentatively scheduled to start
Foundation & waterproofing work will be ongoing adjacent to the building core
Excavation & export operations for the garage will continue
Work along Milk Alley tentatively scheduled to start
MBTA elevator MEP, parapet and roof work is ongoing
Should you have any questions, please reach out to us at info@discoverUSQ.com.
Thank you,
US2
Gilbane Building Company
Cranshaw Construction