Planned Activities for the Week of 9/20/2021 - 9/26/2021

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Site work for pile installation

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Utility work will continue along Charlestown and at the future MBTA facilities

  • Eversource’s cable pull off of Somerville Ave to the site is tentatively scheduled to start

  • Foundation & waterproofing work will be ongoing adjacent to the building core

  • Excavation & export operations for the garage will continue

  • Work along Milk Alley tentatively scheduled to start

  • MBTA elevator MEP, parapet and roof work is ongoing

Should you have any questions, please reach out to us at info@discoverUSQ.com.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction

Previous
Previous

Planned Activities for the Week of 9/27/2021 - 10/3/2021

Next
Next

Planned Activities for the Week of 9/13/2021 - 9/19/2021