Planned Activities for the Week of 9/13/2021 - 9/19/2021

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Mobilize pile driving equipment

  • Continue Site Work

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Utility work will continue along Charlestown and at the future MBTA bike storage & temp employee facility

  • Eversource primary pull off of Somerville Ave on to Milk Alley is ongoing

  • Foundation & building core work is ongoing

  • Excavation for the garage is to start on Monday

  • Work along Milk Alley tentatively schedule to begin

  • MBTA elevator glass, parapet and MEP work is ongoing


Should you have any questions, please reach out to us at info@discoverUSQ.com.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction