Planned Activities for the Week of 11/22/2021 - 11/28/2021

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Pile Delivery

  • Driving Piles

  • Cutting Piles

  • Demolition and export of excess piles

  • Site Prep

Note: There will be large/vibratory pile driving equipment used on Monday, Tuesday and Wednesday.

Weekend Work (11/20):

  • Demolition and export of excess piles

  • Site Prep

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Eversource’s cable pull off of Somerville Ave to Lot 5 will continue next week

  • Foundation & waterproofing work will be ongoing

  • Concrete placements will continue at the building core walls & slabs

  • Excavation, stockpile & export of soils will continue

  • Retaining wall cap cut and rail install along Milk Alley will continue, north working south

  • Support of excavation for storm water storage installation will continue at SE corner of site

  • MBTA elevator, bike shelter & temporary trailer work will continue

  • Steel erection and precast plank install at the tower will continue

Note: There will be large/vibratory equipment used on the site on Monday, Tuesday, Wednesday & Friday of next week working adjacent to Allen Street gate.

Should you have any questions, please reach out to us at info@discoverUSQ.com.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction

Previous
Previous

Planned Activities for the Week of 11/29/2021 - 12/5/2021

Next
Next

Planned Activities for the Week of 11/15/2021 - 11/21/2021