10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Remove Pile Driving Rig
Form, Reinforce & Place Service & Freight Elevator Pit Slabs
Form & Reinforce Mat Slab, Elevator Pit Walls
Weekend Work (12/11):
Form & Reinforce Mat Slab, Elevator Pit Walls
Note: Concrete trucks will be in and out throughout the week.
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Eversource’s manhole work along Milk Alley for temporary power
Mid-rise foundation waterproofing work
Concrete placements at the building core slab & foundation
Retaining wall rail install along Milk Alley
D2.4 soil export and stormwater storage system install work
MBTA elevator, bike shelter & temporary trailer work
Steel erection and precast plank install at the tower
Mid-rise steel erection will commence
Weekend Work (12/11):
ACS form removal at the building core
Note: Excavation operations will continue at the D2.4 site, adjacent to the Allen Street gate, Monday - Friday.