Planned Activities for the Week of 12/13/2021 - 12/19/2021

10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Remove Pile Driving Rig

  • Form, Reinforce & Place Service & Freight Elevator Pit Slabs

  • Form & Reinforce Mat Slab, Elevator Pit Walls

Weekend Work (12/11):

  • Form & Reinforce Mat Slab, Elevator Pit Walls

Note: Concrete trucks will be in and out throughout the week.

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Eversource’s manhole work along Milk Alley for temporary power

  • Mid-rise foundation waterproofing work

  • Concrete placements at the building core slab & foundation

  • Retaining wall rail install along Milk Alley

  • D2.4 soil export and stormwater storage system install work

  • MBTA elevator, bike shelter & temporary trailer work

  • Steel erection and precast plank install at the tower

  • Mid-rise steel erection will commence

Weekend Work (12/11):

  • ACS form removal at the building core

Note: Excavation operations will continue at the D2.4 site, adjacent to the Allen Street gate, Monday - Friday.

Should you have any questions, please reach out to us at info@discoverUSQ.com.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction

Previous
Previous

Planned Activities for the Week of 12/20/2021 - 12/26/2021

Next
Next

Planned Activities for the Week of 12/6/2021 - 12/12/2021