Planned Activities for the Week of 12/6/2021 - 12/12/2021
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Prep Site /Cut-Off Piles to Design Elevation
Remove concrete rubble & grade to bottom of Mat & Pile Caps
Remove Pile Driving Rig
Mobilize Concrete Contractor
Form, Reinforce & Place Service & Freight Elevator
Pit Concrete Slabs
Note: There will be large vibratory pile driving equipment used to prep site /cut-off piles to design elevation and remove concrete rubble & grade to bottom of mat & pile caps
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Eversource’s temporary power install
Foundation & waterproofing work adjacent to the building core
Core ACS form removal
Excavation & export of soils
Retaining wall guard rail install along Milk Alley
D2.4 storm water trap install
MBTA elevator, bike shelter & temporary trailer work
Steel erection and precast plank install at the tower
Mid-rise steel erection will commence
Weekend Work (12/4):
ACS form removal at the building core
Note: There will be large/vibratory equipment used at the D2.4 site, adjacent to the Allen Street gate.
Should you have any questions, please reach out to us at info@discoverUSQ.com.
Thank you,
US2
Gilbane Building Company
Cranshaw Construction