10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)

Gilbane Building Company

The following activities are expected to take place:

  • Prep Site /Cut-Off Piles to Design Elevation

  • Remove concrete rubble & grade to bottom of Mat & Pile Caps

  • Remove Pile Driving Rig

  • Mobilize Concrete Contractor

  • Form, Reinforce & Place Service & Freight Elevator

  • Pit Concrete Slabs

Note: There will be large vibratory pile driving equipment used to prep site /cut-off piles  to design elevation and remove concrete rubble & grade to bottom of mat & pile caps

20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)

Cranshaw Construction

The following activities are expected to take place:

  • Eversource’s temporary power install

  • Foundation & waterproofing work adjacent to the building core

  • Core ACS form removal

  • Excavation & export of soils

  • Retaining wall guard rail install along Milk Alley

  • D2.4 storm water trap install

  • MBTA elevator, bike shelter & temporary trailer work

  • Steel erection and precast plank install at the tower

  • Mid-rise steel erection will commence

Weekend Work (12/4):

  • ACS form removal at the building core

Note: There will be large/vibratory equipment used at the D2.4 site, adjacent to the Allen Street gate. 

Should you have any questions, please reach out to us at info@discoverUSQ.com.

Thank you,

US2
Gilbane Building Company
Cranshaw Construction

Previous
Previous

Planned Activities for the Week of 12/13/2021 - 12/19/2021

Next
Next

Planned Activities for the Week of 11/29/2021 - 12/5/2021