Planned Activities for the Week of 12/20/2021 - 12/26/2021
10 Prospect Street (D2.1) – Future Life Sciences Building (closest to Somerville Avenue)
Gilbane Building Company
The following activities are expected to take place:
Mat/Tower Crane Foundation form & reinforce
Place Mat/Tower Crane Foundation
No weekend work is scheduled.
Note: Concrete trucks will be in and out throughout the week.
*** On Wednesday 12/22 the mat slab concrete pour is scheduled. Work will start at 5am and over the course of the day, concrete trucks will be consistently delivering concrete to the site. ***
20-50 Prospect Street (D2.2-D2.3) – Future Apartment Building (closest to MBTA Station)
Cranshaw Construction
The following activities are expected to take place:
Eversource’s work along Milk Alley for temporary power
Mid-rise foundation waterproofing work
Retaining wall rail install along Milk Alley
D2.4 soil export and stormwater storage system install work
MBTA elevator, bike shelter & temporary trailer work
Steel erection and precast plank install at the tower
Mid-rise steel erection on the north
Tower temporary tarp enclosure for winter conditions
No weekend work is scheduled.
Note: Excavation operations will continue at the D2.4 site, adjacent to the Allen Street gate, Monday - Friday.